Grid queue chaos continues admits Ofgem

Staff
By Staff
5 Min Read

Ofgem has launched an urgent investigation into delays to grid connections after admitting that most projects in the newly reformed queue have been pushed back, rather than brought forward.

The regulator says the reforms have succeeded in removing large amounts of speculative capacity and created a more credible pipeline of projects – but many developers are now receiving connection dates that are later than the ones they held before the overhaul.

That is exactly the outcome the reforms were supposed to avoid.

Protected projects and those dealt with in Phase One are now the focus of an inquiry into why dates have slipped despite the queue being cleared of projects considered speculative, unready or unlikely to proceed.

Ofgem says some schemes have moved backwards materially and it wants NESO and the network companies to explain what has happened, whether delays differ between regions and what can be done to accelerate projects which are ready to build.

The issue is becoming increasingly important because developers make investment decisions around connection dates. A solar farm, battery, data centre or industrial project which suddenly finds its grid date slipping by several years can face higher financing costs, delayed revenues and problems with land, planning and supply-chain contracts.

Ofgem is now demanding much more information about how revised offers have been calculated and why dates have changed.

NESO will be required to publish more detail on the assumptions used in planning the network, while connections data will be updated more openly as new offers are issued. The regulator also wants developers to be able to see the works needed for their projects and understand why those works affect the date they can connect.

Projects which fail to make sufficient progress will face greater scrutiny as Ofgem tries to stop the queue filling up again, particularly in heavily oversubscribed areas such as battery storage and data centres.

Ofgem is also turning its attention to what happens when the delay is caused by the network rather than the developer.

It is considering stronger automatic compensation for customers whose connections are held up by network companies – and says it sees no reason why such provisions could not already be written into connection agreements.

Network companies could also face financial penalties under the next RIIO price control, with Ofgem planning to consult in December on a new connections incentive that would reward good performance and penalise poor delivery.

The regulator has gone further by warning that if its inquiry uncovers a material breach of licence obligations by NESO or any network company it will consider enforcement action.

The latest intervention exposes an uncomfortable problem with the connections reforms.

The old queue had grown to several times the capacity Britain is ever likely to need, with viable schemes stuck behind projects that had little prospect of being built. Clearing those projects was supposed to allow ready schemes to move forward faster.

Instead many developers are now being told they will have to wait even longer.

Ofgem says the amount of generation, storage and demand seeking to connect is doubling every few years and accepts that network construction cannot keep pace without a significant increase in delivery.

Its inquiry will now have to establish whether the revised dates reflect genuine physical constraints on the network or whether poor planning and delivery by NESO and the transmission companies have simply replaced one connections problem with another.

The first detailed picture of what has happened will be published in Ofgem’s Infrastructure Progress Report in February.